Interior trim is complete.
Interior painting is almost complete. It should be finished by tomorrow.
Countertops will be installed Tuesday and Wednesday of next week.
Electrical, plumbing and HVAC trim outs will commence next week.
Tabby porches were poured today.
Garden wall brick cap will be complete early next week.
Hardscapes will begin next week.
Brick Pavers were delivered today.
Stair handrail has been fabricated. Finish will be applied next week and installed once hardwood floor finish is complete.
We took delivery of the 20-6” caliper Live Oak Trees this week and they have been installed.
Drip irrigation for these trees has been installed.
Pavers were delivered today. Installation of pavers behind curb will commence.
The Riceland Way gas street lanterns have been delivered. We are working with Atlanta Gas Light on gas line installation.
We are working on the layout of the fire pit area. Submittal to the ARB will be soon.
Filling and compaction of the lot 50 and the alley is planned to start soon.
We are working on landscaping options for the western end of the Village Green.