Interior Paint will be complete tomorrow.
Countertops have been installed.
Plumbing trim out is under way.
Lighting has been delivered.
Electrical and HVAC trim outs will begin Monday.
Garden wall brick cap is complete.
Hardscapes have begun. Stone patio is complete. Brick paver pathways are complete. Gravel pathways are underway.
Stair handrail has been fabricated. Finish will be applied next week and installed once hardwood floor finish is complete.
Hardwood floor finish is scheduled for the week of the 14th.
Garage doors should be installed next week.
Shower glass and mirrors are scheduled for the 17th.
Installation of pavers behind curb is complete. Sanding and compaction is underway.
The Riceland Way gas street lanterns have been delivered. We are working with Atlanta Gas Light on gas line installation.
We are working on the layout of the fire pit area. Submittal to the ARB will be soon. We have started bringing in fill material for this area.
Filling and compaction of the lot 50 and the alley access is planned to start soon.
The Citrus tree garden and pathways will commence next week at the western end of the Village Green.
The Riceland Way fountain is installed. Paver patio and landscaping will commence next week.
We are working with Georgia Power to get power to the island for the fountain pump and landscape lighting.
We have schedule the top coat paving of Riceland Way for late October.