SILK HOPE CONSTRUCTION UPDATE
February 3, 2020
Lot SH48 | 96 Riceland Way—Longleat Village Home at Silk Hope Interior Trim is complete. Exterior door hardware will be complete tomorrow. Kitchen and Bath Cabinets anticipated delivery and installation as soon as painting is complete. Interior painting will be complete in a week and half. Electrical, plumbing, HVAC and A/V trim outs to begin…