Lot SH48 | 96 Riceland Way—Longleat Village Home at Silk Hope
- Exterior door hardware is installed.
- Kitchen and Bath Cabinets installation will being on the 17th.
- Interior painting will be complete in a week.
- Electrical, plumbing, HVAC and A/V trim outs to begin the week of the 17th.
- Carpet has been selected.
- Hardwood floor finishing to being at the end of this month.