Lot SH48 | 96 Riceland Way—Longleat Village Home at Silk Hope
- Range hood shroud needed some additional modification and will be installed once complete.
- Bathroom countertops will be installed next Thursday. Fireplace surround to follow.
- Interior and exterior paint touch ups will be complete next week.
- HVAC and A/V trim outs are complete.
- Electrical and plumbing trim outs are well underway and will be complete once remaining tops are installed next week.
- Hardwood floor finishing will begin on the 16th.
- Stair handrail is in production and will be installed once complete.
- Appliance installation is scheduled for the week of the 23rd.
Sitework and Landscaping
- We are working on the fountain pump.