Lot SH48 | 96 Riceland Way—Longleat Village Home at Silk Hope
- Range hood shroud skeleton is installed ready for drywall.Bathroom and laundry countertops are installed.Fireplace surround is underway.
Interior and exterior paint touch ups are underway.
Electrical trim out is complete.
Plumbing trim out will be complete early next week.
Hardwood floor finishing will begin next week.
Stair handrail is in production and will be installed once complete.
Appliance installation is scheduled for the week of the 23rd.
Bathroom mirror framework installation will begin next week.
Sitework and Landscaping
- We are working on the fountain pump.