Plumbing trim out is complete at 96 Riceland Way. Final touch ups and tweaks have been ongoing this week for plumbing and electrical. Some paint and drywall touch ups were worked on early in the week. The final touch ups will occur once floor finishing is complete. Fire place hearth is in place and surround to follow. Hardwood floor finishing is underway and the first two coats will be on by mid-week. The final coat will be applied once all touch ups are complete. Bathroom mirror frameworks was installed and mirrors will be ordered on Monday. Stair handrail will be installed once first two coats are on the hardwood floors. The kitchen vent shroud will be removed and reworked at the cabinet shop and then reinstalled. Appliances are scheduled for the 30th but may get pushed a little if kitchen vent shroud is not re-installed by then. Outlined below is last week’s progress and this week’s work schedule:
Range hood shroud skeleton will be removed and reworked.
Bathroom paper holders are installed and mirror framework installed.
Fireplace hearth is installed and surround to follow.
Interior and exterior paint touch ups are underway.
Electrical and plumbing touch ups and tweaks are complete.
Plumbing trim out is complete.
Hardwood floor finishing is underway. First two coats will be applied next week. Final coat once everything is complete.
Stair handrail is in production and will be installed after first two coats are applied to hardwood floors.
Appliance installation is scheduled for the week of the 30th if vent shroud is back in place.
We are working on the fountain pump. This will be complete early next week.