96 Riceland Way is coming to a close in the next week or so! The range vent hood shroud has been rebuilt and installed. Tile backsplash has been installed. All appliances except for the range and vent hood have been installed and they will be installed on Monday as well as the dishwasher will be connected. The butler’s pantry wood countertop has been installed. The balance of the kitchen crown will be installed on Monday. The final hardwood floor finish will be applied next Thursday. Final paint touch ups will occur next week as well. Will be calling for final inspection with the city hopefully next Friday. Outlined below is this week’s progress and next week’s work schedule:
Range hood shroud installed.
Complete kitchen crown next week.
Appliances are installed. Range and Vent installed on Monday.
Tile backsplash is installed.
Wood countertop in butler’s pantry is installed.
Final hardwood floor finish is scheduled for Thursday.
Final Paint touch ups next week.
Electrical and Plumbing punch will be completed next week.